Submarine power transmission business in Germany
| Overview of the business | ||||
|---|---|---|---|---|
| Project overview | Operating and maintaining following four submarine transmission cables which run from a wind power plant located in an offshore area of the North Sea | |||
| BorWin1 | BorWin2 | DolWin2 | HelWin2 | |
| Capacity | 400MW | 800MW | 920MW | 690MW |
| Transmission Line Length | 200 km On land 75km Submarine 125km |
200 km On land 75km Submarine 125km |
135 km On land 90km Submarine 45km |
130 km On land 45km Submarine 85km |
| Sponsors | Chubu Electric Power (12.2%), CIP (25%), Mitsubishi HC Capital (11.8%), TenneT Holding B.V. (51%) | |||