Chubu Electric Power has decided to construct the Atsumi II Wind Power Station (the "Station") in Konakayama-cho, Tahara City, Aichi Prefecture.
The Station is an onshore wind farm with a generation output of 21,000 kW, with construction scheduled to begin in May 2025 and operation to commence in November 2027.
We will proceed with the development in consideration of the natural environment and with the understanding and cooperation of the local community and other related parties.
The Chubu Electric Power Group has positioned renewable energy as one of its main power sources that will contribute to achieving a carbon-free society as well as enhancing energy self-sufficiency, and we will continue active development in order to achieve our goal of "an expansion over 3.2 million kW through ownership, construction, and maintenance of renewable energy plants by around 2030".
Overview of Atsumi II Wind Power Station
Power output |
21,000 kW(Single unit output 4,200 kW x 5 units) |
---|---|
Construction plan location |
Konakayama-cho, Tahara City, Aichi Prefecture |
Annual power output |
Approx. 51.5 million kWh |
CO2 reduction |
About 23,000 tons per year |
Scheduled start of construction |
May 2025 |
Scheduled start of operation |
November 2027 |